Phase 10: Multi-Question Schema
- 4 plans in 3 waves
- Wave 1: Schema & types (01)
- Wave 2: Manager implementations + unit tests (02, 03 parallel)
- Wave 3: E2E tests (04)
- Ready for execution
|