Commit Graph

13 Commits

Author SHA1 Message Date
Lukas May
5c07a4c4cf docs(01.1-03): complete process module testing and events plan
Tasks completed: 2/2
- Write unit tests for ProcessRegistry and ProcessManager
- Refactor ProcessManager to emit events via event bus

SUMMARY: .planning/phases/01.1-hexagonal-architecture/01.1-03-SUMMARY.md
2026-01-30 14:04:57 +01:00
Lukas May
573a704230 docs(01.1-04): complete logging module tests and events plan
Tasks completed: 2/2
- Write unit tests for LogManager and ProcessLogWriter
- Add event emission to ProcessLogWriter

SUMMARY: .planning/phases/01.1-hexagonal-architecture/01.1-04-SUMMARY.md
2026-01-30 14:04:56 +01:00
Lukas May
63e603709d docs(01.1-05): complete server tests and events plan
Tasks completed: 2/2
- Write unit tests for CoordinationServer
- Add event emission to server and shutdown handler

SUMMARY: .planning/phases/01.1-hexagonal-architecture/01.1-05-SUMMARY.md
2026-01-30 14:04:47 +01:00
Lukas May
f2a7b3f77a docs(01.1-02): complete tRPC foundation plan
Tasks completed: 2/2
- Install tRPC dependencies and create router foundation
- Define procedures matching HTTP endpoints with tests

SUMMARY: .planning/phases/01.1-hexagonal-architecture/01.1-02-SUMMARY.md
2026-01-30 13:59:53 +01:00
Lukas May
e72ffdd800 docs(01.1-01): complete event bus foundation plan
Tasks completed: 3/3
- Install and configure Vitest test framework
- Create EventBus port interface and EventEmitter adapter
- Define domain events with typed payloads and tests

SUMMARY: .planning/phases/01.1-hexagonal-architecture/01.1-01-SUMMARY.md
2026-01-30 13:56:20 +01:00
Lukas May
5c5632dccf docs(01.1): create phase plan
Phase 01.1: Hexagonal Architecture
- 6 plans in 3 waves
- Wave 1: Event bus + tRPC foundation (parallel)
- Wave 2: Process, logging, server module refactors (parallel)
- Wave 3: CLI tRPC integration
- Ready for execution
2026-01-30 13:49:07 +01:00
Lukas May
1da8e4f795 docs(1.1): capture phase context
Phase 1.1: Hexagonal Architecture
- Vision and goals documented
- Essential requirements identified
- Scope boundaries defined
2026-01-30 13:42:53 +01:00
Lukas May
6f64ec3e8c docs(01-05): complete server mode plan
Tasks completed: 2/2
- HTTP server with health endpoint and PID file
- Graceful shutdown with signal handlers

SUMMARY: .planning/phases/01-core-infrastructure/01-05-SUMMARY.md

Phase 1 (Core Infrastructure) complete.
2026-01-30 13:28:15 +01:00
Lukas May
f117227fed docs(01-04): complete logging infrastructure plan
Tasks completed: 2/2
- Create log directory management
- Create per-process log writer

SUMMARY: .planning/phases/01-core-infrastructure/01-04-SUMMARY.md
2026-01-30 13:18:17 +01:00
Lukas May
3e7b9f24bd docs(01-03): complete process management plan
Tasks completed: 2/2
- Create process types and registry
- Create process manager with spawn/stop

SUMMARY: .planning/phases/01-core-infrastructure/01-03-SUMMARY.md
2026-01-30 13:17:03 +01:00
Lukas May
57a4d938fa docs(01-02): complete CLI entry point plan
Tasks completed: 2/2
- Create CLI with commander
- Enable global installation via npm link

SUMMARY: .planning/phases/01-core-infrastructure/01-02-SUMMARY.md
2026-01-30 13:14:28 +01:00
Lukas May
5329349878 docs(01-01): complete project foundation plan
Tasks completed: 2/2
- Initialize Node.js project with TypeScript and ESM
- Create source structure and entry point

SUMMARY: .planning/phases/01-core-infrastructure/01-01-SUMMARY.md
2026-01-30 13:11:19 +01:00
Lukas May
074f79b855 docs(01): create phase 1 plan
Phase 01: Core Infrastructure
- 5 plans in 3 waves
- Wave 1: Project foundation (01-01)
- Wave 2: CLI, process mgmt, logging (01-02, 01-03, 01-04) [parallel]
- Wave 3: Server mode & shutdown (01-05)
- Ready for execution
2026-01-30 13:06:38 +01:00