Tasks completed: 2/2 - Create recovery/resume scenario tests - Create extended agent Q&A scenario tests SUMMARY: .planning/phases/09-extended-scenarios/09-02-SUMMARY.md
3.0 KiB
3.0 KiB
phase, plan, subsystem, tags, requires, provides, affects, tech-stack, key-files, key-decisions, patterns-established, duration, completed
| phase | plan | subsystem | tags | requires | provides | affects | tech-stack | key-files | key-decisions | patterns-established | duration | completed | ||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 09-extended-scenarios | 02 | testing |
|
|
|
|
|
|
|
3min | 2026-01-31 |
Phase 09 Plan 02: Recovery & Resume E2E Tests Summary
E2E tests proving recovery after interruption and extended agent Q&A flows work correctly with database as source of truth
Performance
- Duration: 3 min
- Started: 2026-01-31T14:42:03Z
- Completed: 2026-01-31T14:45:08Z
- Tasks: 2
- Files modified: 1
Accomplishments
- 8 E2E tests proving recovery and Q&A scenarios work correctly
- Recovery tests validating database as source of truth for state persistence
- Q&A tests validating full agent:waiting -> agent:resumed -> agent:stopped state machine
- All 34 E2E tests pass with no regressions
Task Commits
Each task was committed atomically:
- Task 1: Create recovery/resume scenario tests -
62b13d8(test) - Task 2: Create extended agent Q&A scenario tests -
62b13d8(test - combined with Task 1)
Note: Both tasks implemented in single test file with two describe blocks.
Files Created/Modified
src/test/e2e/recovery-scenarios.test.ts- 8 tests across 2 describe blocks (Recovery after interruption, Agent Q&A extended scenarios)
Decisions Made
- Database is source of truth: Recovery tests verify that queue state survives because task status is persisted to DB, not just in-memory.
- Blocked task recovery via DB update: Since no
unblockTaskmethod exists, tests update task status via repository then re-queue. - Combined task implementation: Both recovery and Q&A tests implemented in single file for cohesion.
Deviations from Plan
None - plan executed exactly as written.
Issues Encountered
None.
User Setup Required
None - no external service configuration required.
Next Phase Readiness
- All 34 E2E tests pass (6 happy path + 14 edge cases + 6 extended + 8 recovery/Q&A)
- Phase 9 complete - all extended scenarios validated
- v1.1 Test Infrastructure milestone complete
Phase: 09-extended-scenarios Completed: 2026-01-31