Tasks completed: 2/2 - Create CLI with commander - Enable global installation via npm link SUMMARY: .planning/phases/01-core-infrastructure/01-02-SUMMARY.md
1.2 KiB
1.2 KiB
Project State
Project Reference
See: .planning/PROJECT.md (updated 2026-01-30)
Core value: Coordinate multiple Claude Code agents without losing track or stepping on each other. Current focus: Phase 1 — Core Infrastructure
Current Position
Phase: 1 of 7 (Core Infrastructure) Plan: 2 of 5 in current phase Status: In progress Last activity: 2026-01-30 — Completed 01-02-PLAN.md
Progress: ███░░░░░░░ 10%
Performance Metrics
Velocity:
- Total plans completed: 2
- Average duration: 1.5 min
- Total execution time: 3 min
By Phase:
| Phase | Plans | Total | Avg/Plan |
|---|---|---|---|
| 1 | 2/5 | 3 min | 1.5 min |
Recent Trend:
- Last 5 plans: 01-01 (2 min), 01-02 (1 min)
- Trend: Accelerating
Accumulated Context
Decisions
Decisions are logged in PROJECT.md Key Decisions table. Recent decisions affecting current work:
- 01-01: Merged Tasks 1 and 2 since build verification required source files
- 01-02: Task 2 required no code changes - existing bin config was correct
Pending Todos
None yet.
Blockers/Concerns
None yet.
Session Continuity
Last session: 2026-01-30 Stopped at: Completed 01-02-PLAN.md Resume file: None