docs(21-06): complete integration smoke test plan

Tasks completed: 2/2
- Run full build verification (TypeScript, Vite, tests)
- Full integration smoke test (human-verified, approved)

SUMMARY: .planning/phases/21-polish-integration/21-06-SUMMARY.md
This commit is contained in:
Lukas May
2026-02-05 09:16:31 +01:00
parent 51c26d6d19
commit 111ed0962f
3 changed files with 107 additions and 15 deletions

View File

@@ -14,7 +14,7 @@ None
-**v1.1 Test Infrastructure** - Phases 7-9 (shipped 2026-01-31)
-**v1.2 Architect & Multi-Question** - Phases 10-13 (shipped 2026-02-02)
-**v1.3 Parallel Execution & UI Design** - Phases 14-15 (shipped 2026-02-02)
- 🚧 **v2.0 Frontend** - Phases 16-21 (in progress)
- **v2.0 Frontend** - Phases 16-21 (shipped 2026-02-05)
## Phases
@@ -244,7 +244,7 @@ Plans:
</details>
### 🚧 v2.0 Frontend (In Progress)
### v2.0 Frontend (SHIPPED 2026-02-05)
**Milestone Goal:** Build the web UI from v1.3 wireframes using React + Vite with real-time tRPC subscriptions
@@ -322,12 +322,12 @@ Plans:
**Plans**: 6 plans
Plans:
- [ ] 21-01: Error Boundary & Toast Notifications
- [ ] 21-02: Skeleton Loading States
- [x] 21-01: Error Boundary & Toast Notifications
- [x] 21-02: Skeleton Loading States
- [x] 21-03: Cross-Screen Navigation & Mobile Responsive
- [x] 21-04: Subscription Error Handling
- [ ] 21-05: Code Splitting & Performance
- [ ] 21-06: Integration Smoke Test
- [x] 21-05: Code Splitting & Performance
- [x] 21-06: Integration Smoke Test
## Progress
@@ -358,7 +358,7 @@ Phases execute in numeric order: 1 → 1.1 → 2 → 3 → 4 → 5 → 6 → 7
| 18. Initiative Detail | v2.0 | 4/4 | Complete | 2026-02-04 |
| 19. Agent Inbox | v2.0 | 4/4 | Complete | 2026-02-04 |
| 20. Real-time Subscriptions | v2.0 | 2/2 | Complete | 2026-02-04 |
| 21. Polish & Integration | v2.0 | 4/6 | In progress | - |
| 21. Polish & Integration | v2.0 | 6/6 | Complete | 2026-02-05 |
---
*Roadmap created: 2026-01-30*
@@ -366,3 +366,4 @@ Phases execute in numeric order: 1 → 1.1 → 2 → 3 → 4 → 5 → 6 → 7
*v1.1 shipped: 2026-01-31 (8 plans, 3 phases)*
*v1.2 shipped: 2026-02-02 (21 plans, 4 phases)*
*v1.3 shipped: 2026-02-02 (11 plans, 2 phases)*
*v2.0 shipped: 2026-02-05 (27 plans, 6 phases)*

View File

@@ -9,19 +9,19 @@ See: .planning/PROJECT.md (updated 2026-02-04)
## Current Position
Phase: 21 of 21 (Polish & Integration) - In progress
Plan: 5 of 6 in current phase
Status: Completed 21-05 (Code Splitting & Data-Fetching Performance)
Last activity: 2026-02-05 - Completed 21-05-PLAN.md (route code splitting + PlanTasksFetcher fix)
Phase: 21 of 21 (Polish & Integration) - Phase complete
Plan: 6 of 6 in current phase
Status: Completed 21-06 (Integration Smoke Test)
Last activity: 2026-02-05 - Completed 21-06-PLAN.md (full build verification + human smoke test)
Progress: █████████░ 99%
Progress: ██████████ 100%
## Performance Metrics
**Velocity:**
- Total plans completed: 74
- Total plans completed: 75
- Average duration: 3 min
- Total execution time: 209 min
- Total execution time: 211 min
**By Phase (v1.0):**
@@ -249,6 +249,7 @@ Recent decisions affecting current work:
- 21-04: SpawnArchitectDropdown already covered by 21-01 — verification task was no-op
- 21-05: autoCodeSplitting: true on TanStackRouterVite plugin — automatic route splitting without manual .lazy.tsx files
- 21-05: PlanTasksFetcher onTasks moved to useEffect to prevent setState-during-render loops
- 21-06: No code changes needed — verification-only plan confirming all Phase 21 work integrates correctly
### Pending Todos
@@ -271,5 +272,5 @@ None.
## Session Continuity
Last session: 2026-02-05
Stopped at: Completed 21-05 (Code Splitting & Data-Fetching Performance)
Stopped at: Completed 21-06 (Integration Smoke Test) - Phase 21 complete, v2.0 milestone complete
Resume file: None

View File

@@ -0,0 +1,90 @@
---
phase: 21-polish-integration
plan: 06
subsystem: ui
tags: [integration-test, smoke-test, verification, frontend]
# Dependency graph
requires:
- phase: 21-04
provides: Subscription error handling with toast notifications
- phase: 21-05
provides: Code splitting, PlanTasksFetcher render fix
provides:
- Verified frontend ready to ship as v2.0
- Full build pipeline confirmed (TypeScript, Vite, tests)
- Human-verified all screens, navigation, error handling, and loading states
affects: []
# Tech tracking
tech-stack:
added: []
patterns: []
key-files:
created: []
modified: []
key-decisions:
- "No code changes needed — verification-only plan confirming all Phase 21 work integrates correctly"
patterns-established: []
# Metrics
duration: 2min
completed: 2026-02-05
---
# Phase 21 Plan 06: Integration Smoke Test Summary
**Full build pipeline and human-verified end-to-end smoke test confirming v2.0 frontend readiness**
## Performance
- **Duration:** 2 min
- **Started:** 2026-02-05
- **Completed:** 2026-02-05
- **Tasks:** 2
- **Files modified:** 0
## Accomplishments
- Full build verification passed: TypeScript (backend + frontend), Vite production build, all tests green
- No `console.error` calls remaining in component source files
- Human smoke test approved: dashboard, detail, inbox, error handling, 404, loading states, and navigation all verified end-to-end
## Task Commits
This was a verification-only plan with no code changes:
1. **Task 1: Run full build verification** - (no commit - verification only)
2. **Task 2: Full integration smoke test** - (no commit - human-verify checkpoint, approved)
**Plan metadata:** committed with SUMMARY + STATE + ROADMAP update
## Files Created/Modified
None - verification-only plan.
## Decisions Made
None - followed plan as specified. All prior Phase 21 work verified as correct.
## Deviations from Plan
None - plan executed exactly as written.
## Issues Encountered
None
## User Setup Required
None - no external service configuration required.
## Next Phase Readiness
- Phase 21 complete. All 6 plans finished.
- v2.0 Frontend milestone ready to ship.
- All screens verified: dashboard, initiative detail, agent inbox, 404
- Error handling confirmed: toast notifications, persistent SSE disconnect warning, graceful degradation
- Loading states confirmed: skeleton loading cards, rows, and layout
- Navigation confirmed: cross-screen links, mobile responsive drill-down, back buttons
---