docs(21-06): complete integration smoke test plan

Tasks completed: 2/2
- Run full build verification (TypeScript, Vite, tests)
- Full integration smoke test (human-verified, approved)

SUMMARY: .planning/phases/21-polish-integration/21-06-SUMMARY.md
This commit is contained in:
Lukas May
2026-02-05 09:16:31 +01:00
parent 51c26d6d19
commit 111ed0962f
3 changed files with 107 additions and 15 deletions

View File

@@ -9,19 +9,19 @@ See: .planning/PROJECT.md (updated 2026-02-04)
## Current Position
Phase: 21 of 21 (Polish & Integration) - In progress
Plan: 5 of 6 in current phase
Status: Completed 21-05 (Code Splitting & Data-Fetching Performance)
Last activity: 2026-02-05 - Completed 21-05-PLAN.md (route code splitting + PlanTasksFetcher fix)
Phase: 21 of 21 (Polish & Integration) - Phase complete
Plan: 6 of 6 in current phase
Status: Completed 21-06 (Integration Smoke Test)
Last activity: 2026-02-05 - Completed 21-06-PLAN.md (full build verification + human smoke test)
Progress: █████████░ 99%
Progress: ██████████ 100%
## Performance Metrics
**Velocity:**
- Total plans completed: 74
- Total plans completed: 75
- Average duration: 3 min
- Total execution time: 209 min
- Total execution time: 211 min
**By Phase (v1.0):**
@@ -249,6 +249,7 @@ Recent decisions affecting current work:
- 21-04: SpawnArchitectDropdown already covered by 21-01 — verification task was no-op
- 21-05: autoCodeSplitting: true on TanStackRouterVite plugin — automatic route splitting without manual .lazy.tsx files
- 21-05: PlanTasksFetcher onTasks moved to useEffect to prevent setState-during-render loops
- 21-06: No code changes needed — verification-only plan confirming all Phase 21 work integrates correctly
### Pending Todos
@@ -271,5 +272,5 @@ None.
## Session Continuity
Last session: 2026-02-05
Stopped at: Completed 21-05 (Code Splitting & Data-Fetching Performance)
Stopped at: Completed 21-06 (Integration Smoke Test) - Phase 21 complete, v2.0 milestone complete
Resume file: None