docs(10-04): complete E2E test updates plan
Tasks completed: 2/2 - Verified existing E2E tests use questions array format - Added multi-question E2E test Phase 10: Multi-Question Schema complete (4/4 plans) SUMMARY: .planning/phases/10-multi-question-schema/10-04-SUMMARY.md
This commit is contained in:
@@ -155,7 +155,7 @@ Plans:
|
||||
- [x] 10-01: Schema & Type Updates
|
||||
- [x] 10-02: Manager Implementation
|
||||
- [x] 10-03: TestHarness & Test Updates
|
||||
- [ ] 10-04: CLI & tRPC Integration
|
||||
- [x] 10-04: E2E Test Updates
|
||||
|
||||
#### Phase 11: Architect Agent
|
||||
**Goal**: Agent modes for concept refinement (questioning) and phase breakdown (persisting to ROADMAP.md)
|
||||
@@ -203,7 +203,7 @@ Phases execute in numeric order: 1 → 1.1 → 2 → 3 → 4 → 5 → 6 → 7
|
||||
| 8. E2E Scenario Tests | v1.1 | 2/2 | Complete | 2026-01-31 |
|
||||
| 8.1. Agent Output Schema | v1.1 | 2/2 | Complete | 2026-01-31 |
|
||||
| 9. Extended Scenarios | v1.1 | 2/2 | Complete | 2026-01-31 |
|
||||
| 10. Multi-Question Schema | v1.2 | 3/4 | In progress | - |
|
||||
| 10. Multi-Question Schema | v1.2 | 4/4 | Complete | 2026-01-31 |
|
||||
| 11. Architect Agent | v1.2 | 0/? | Not started | - |
|
||||
| 12. Phase-Task Decomposition | v1.2 | 0/? | Not started | - |
|
||||
| 13. Real Claude E2E Tests | v1.2 | 0/? | Not started | - |
|
||||
|
||||
@@ -10,11 +10,11 @@ See: .planning/PROJECT.md (updated 2026-01-31)
|
||||
## Current Position
|
||||
|
||||
Phase: 10 of 13 (Multi-Question Schema)
|
||||
Plan: 3 of 4 in current phase
|
||||
Status: In progress
|
||||
Last activity: 2026-01-31 — Completed 10-03-PLAN.md
|
||||
Plan: 4 of 4 in current phase
|
||||
Status: Phase complete
|
||||
Last activity: 2026-01-31 — Completed 10-04-PLAN.md
|
||||
|
||||
Progress: ██░░░░░░░░ 15%
|
||||
Progress: ███░░░░░░░ 25%
|
||||
|
||||
## Performance Metrics
|
||||
|
||||
@@ -147,5 +147,5 @@ None.
|
||||
## Session Continuity
|
||||
|
||||
Last session: 2026-01-31
|
||||
Stopped at: Completed 10-03-PLAN.md (TestHarness and Test Updates)
|
||||
Stopped at: Completed 10-04-PLAN.md (E2E Test Updates) — Phase 10 complete
|
||||
Resume file: None
|
||||
|
||||
93
.planning/phases/10-multi-question-schema/10-04-SUMMARY.md
Normal file
93
.planning/phases/10-multi-question-schema/10-04-SUMMARY.md
Normal file
@@ -0,0 +1,93 @@
|
||||
---
|
||||
phase: 10-multi-question-schema
|
||||
plan: 04
|
||||
subsystem: testing
|
||||
tags: [e2e, multi-question, testing, dispatch, coordination]
|
||||
|
||||
# Dependency graph
|
||||
requires:
|
||||
- phase: 10-multi-question-schema (plan 02)
|
||||
provides: Batched answers support via resume()
|
||||
- phase: 10-multi-question-schema (plan 03)
|
||||
provides: TestHarness helpers for questions array
|
||||
provides:
|
||||
- Multi-question E2E test validating batched answers flow
|
||||
- E2E coverage for agent asking multiple questions at once
|
||||
affects: [phase-11-architect-agent]
|
||||
|
||||
# Tech tracking
|
||||
tech-stack:
|
||||
added: []
|
||||
patterns:
|
||||
- "Multi-question E2E validation through dispatch/coordination flow"
|
||||
|
||||
key-files:
|
||||
modified:
|
||||
- src/test/e2e/recovery-scenarios.test.ts
|
||||
|
||||
key-decisions:
|
||||
- "No updates needed for Task 1 - E2E tests already migrated by plan 10-02"
|
||||
|
||||
# Metrics
|
||||
duration: 1min
|
||||
completed: 2026-01-31
|
||||
---
|
||||
|
||||
# Phase 10 Plan 04: E2E Test Updates Summary
|
||||
|
||||
**Added multi-question E2E test validating full dispatch/coordination flow with batched answers**
|
||||
|
||||
## Performance
|
||||
|
||||
- **Duration:** 1 min
|
||||
- **Started:** 2026-01-31T17:07:44Z
|
||||
- **Completed:** 2026-01-31T17:08:42Z
|
||||
- **Tasks:** 2
|
||||
- **Files modified:** 1
|
||||
|
||||
## Accomplishments
|
||||
|
||||
- Verified existing E2E tests already use questions array schema
|
||||
- Added multi-question E2E test with 2 questions and batched answers
|
||||
- Test validates full flow: dispatch -> waiting -> resume with all answers -> completion
|
||||
- All 384 tests pass
|
||||
|
||||
## Task Commits
|
||||
|
||||
Each task was committed atomically:
|
||||
|
||||
1. **Task 1: Update existing E2E tests** - N/A (already completed by plan 10-02)
|
||||
2. **Task 2: Add multi-question E2E test** - `cd84092` (test)
|
||||
|
||||
## Files Created/Modified
|
||||
|
||||
- `src/test/e2e/recovery-scenarios.test.ts` - Added multi-question E2E test scenario
|
||||
|
||||
## Decisions Made
|
||||
|
||||
| Decision | Rationale |
|
||||
|----------|-----------|
|
||||
| Task 1 considered complete | E2E tests were already migrated to questions array format by plan 10-02's downstream fixes |
|
||||
| Test uses 2 questions with options | Validates both question IDs present and answers map works correctly |
|
||||
|
||||
## Deviations from Plan
|
||||
|
||||
None - plan executed as written. Task 1's scope was already covered by prior work.
|
||||
|
||||
## Issues Encountered
|
||||
|
||||
None.
|
||||
|
||||
## User Setup Required
|
||||
|
||||
None - no external service configuration required.
|
||||
|
||||
## Next Phase Readiness
|
||||
|
||||
- Phase 10 complete: all 4 plans finished
|
||||
- Multi-question schema fully implemented and tested
|
||||
- Ready for Phase 11 (Architect Agent)
|
||||
|
||||
---
|
||||
*Phase: 10-multi-question-schema*
|
||||
*Completed: 2026-01-31*
|
||||